Title: Arroyo Canal Fish Screen and Sack Dam Fish Passage Project
Tracking Number: CGB-ED-2025-033
Progress: COMPLETED
Summary: In support of the Restoration Goal of the San Joaquin River Restoration Program, Reclamation proposes to construct and operate a fish screen at Arroyo Canal and fish passage facilities at Sack Dam in Reaches 3 and 4A of the Restoration Area. The proposed modifications are necessary to prevent entrainment into Arroyo Canal and ensure anadromous fish passage at Sack Dam, as required by Paragraphs 11(a)(6) and 11(a)(7) of the Settlement. In 2013, the U.S. Department of the Interior, Bureau of Reclamation (Reclamation), as the federal lead agency and Henry Miller Reclamation District #2131 (HMRD), as the state lead agency, prepared the Arroyo Canal Fish Screen and Sack Dam Fish Passage Project (Project) Environmental Assessment/Initial Study (2013 EA/IS) to analyze and disclose the anticipated environmental impacts of the proposed Project. However, as the Project neared 100 percent design, surveys revealed a significantly higher rate of regional land subsidence than anticipated at Sack Dam, and environmental compliance documentation efforts were paused to allow for design efforts to consider this new information. Since 2013, Reclamation has evaluated several design alternatives that have been eliminated from further consideration for a variety of reasons related to technical and economic feasibility. Reclamation now has sufficient information to analyze the effects of a feasible design alternative for the fish screen and fish passage facilities and is therefore preparing environmental compliance documentation as needed to supplement the previous analyses. Reclamation is preparing a supplemental EA to analyze and disclose any potential impacts to the human environment of the design refinements to the Project beyond those that were analyzed and disclosed in the 2013 EA/IS.
Contact
Phone
Fax
E-Mail
Notes
Becky Victorine (916) 978-4624 916-458-1850 rvictorine@usbr.gov San Joaquin River Restoration Project Office
Status
04/17/2025Supplemental Environmental Assessment and Finding of No Significant Impact posted.
01/22/2025Public review period for Draft Environmental Assessment extended through 1/31/2025. Please send comments to Becky Victorine via the contact information provided above.
12/27/2024Draft Environmental Assessment posted for public review through 1/27/25.
11/14/2024Environmental Assessment in progress.
List of Available Reports
File Report Title File Ext File Size
CGB-ED-2025-033 Arroyo Canal Fish Screen and Sack Dam Fish Passage Project FONSI .pdf 318,501 B
CGB-ED-2025-033 Arroyo Canal Fish Screen and Sack Dam Fish Passage Project Supplemental EA .pdf 9,010,237 B
CGB-ED-2025-033 Arroyo Canal Fish Screen and Sack Dam Fish Passage Project Appendix A .pdf 936,775 B
CGB-ED-2025-033 Arroyo Canal Fish Screen and Sack Dam Fish Passage Project Appendix B .pdf 539,531 B
CGB-ED-2025-033 Arroyo Canal Fish Screen and Sack Dam Fish Passage Project Appendix C .pdf 339,654 B
CGB-ED-2025-033 Arroyo Canal Fish Screen and Sack Dam Fish Passage Project Appendix D .pdf 650,084 B
Draft Environmental Assessment, Arroyo Canal Fish Screen and Sack Dam Fish Passage Project .pdf 13,608,222 B
Draft EA, Appendix A: Operation and Maintenance Plan .pdf 1,244,164 B
Draft EA, Appendix B: Inadvertent Release Plan .pdf 348,961 B
Draft EA, Appendix D: USFWS Species List .pdf 195,641 B