Title: Patterson Irrigation District Two-Drains Project
Summary: Reclamation proposes to provide a $1,500,000 grant to Patterson Irrigation District to help fund construction of three pump stations and four pipelines to reduce the discharge of agricultural drainage flows. About 20,000 linear feet of pipeline would be constructed to capture drain water from the Marshall Road Drain and Spanish Land Grant Drain and recirculate approximately 5,000 acre feet per year of drainage water into the Patterson Irrigation District irrigation system as a supplemental water supply.
Contact
Phone
Fax
E-Mail
Notes
Doug Kleinsmith (916) 978-5034 N/A dkleinsmith@usbr.gov
Status
09/09/2014Draft EA/IS available for review on June 17, 2014. Comments were due by July 18, 2014. FONSI signed and final EA completed on September 3, 2014.
List of Available Reports
File Report Title File Ext File Size
Signed FONSI, Patterson Irrigation District Two-Drains Project .pdf 341 B
Final EA, Patterson Irrigation District Two-Drains Project .pdf 3,308 B
Draft EA/IS, Patterson Irrigation District Two-Drains Project .pdf 2,608 B