Title: | Patterson Irrigation District Two-Drains Project |
---|---|
Summary: | Reclamation proposes to provide a $1,500,000 grant to Patterson Irrigation District to help fund construction of three pump stations and four pipelines to reduce the discharge of agricultural drainage flows. About 20,000 linear feet of pipeline would be constructed to capture drain water from the Marshall Road Drain and Spanish Land Grant Drain and recirculate approximately 5,000 acre feet per year of drainage water into the Patterson Irrigation District irrigation system as a supplemental water supply. |
Contact
|
Phone
|
Fax
|
E-Mail
|
Notes
|
---|---|---|---|---|
Doug Kleinsmith | (916) 978-5034 | N/A | dkleinsmith@usbr.gov |
09/09/2014 | Draft EA/IS available for review on June 17, 2014. Comments were due by July 18, 2014. FONSI signed and final EA completed on September 3, 2014. |
---|
File | Report Title | File Ext | File Size |
---|---|---|---|
Signed FONSI, Patterson Irrigation District Two-Drains Project | 341 B | ||
Final EA, Patterson Irrigation District Two-Drains Project | 3,308 B | ||
Draft EA/IS, Patterson Irrigation District Two-Drains Project | 2,608 B |