Navajo-Gallup Water Supply Project Progresses with Two New Contracts Awarded

Media Contact: Marlon Duke, 801-524-3774, mduke@usbr.gov

For Release: September 20, 2016

Farmington, N.M. – The Bureau of Reclamation recently awarded two new contracts totaling $66.3 million for the Navajo-Gallup Water Supply Project. Those contracts continue construction work on a project that will provide long-term, sustainable water for 43 chapters of the Navajo Nation Reservation, the southwest area of the Jicarilla Apache Reservation and the City of Gallup, New Mexico.

On September 7, 2016, Reclamation awarded a $37 million design-build contract to CH2M for the design and construction of a water treatment plant along the project’s Cutter Lateral. Water for the Cutter Lateral will be supplied from Navajo Reservoir via Cutter Reservoir near Bloomfield, N.M. In addition to a state-of-the-art water treatment plant, work under this contract will include design and construction of a clearwell pumping plant, 500,000 gallon regulating tank, 2,500 square foot operation and maintenance building and 21,400 feet of pipeline. The plant will have a phased water treatment system to accommodate increasing flows over time up to a future total capacity of 5.4 million gallons per day. Work under this contract is scheduled to be completed in the fall of 2019.

On September 8, 2016, Reclamation awarded a second contract valued at $29.3 million to Moltz Constructors, Inc. for construction of Reach 22B of the Cutter Lateral, which will consist of 16 miles of 24-inch diameter pipe and two pumping plants. The pipeline is designed to handle flows up to 9.6 cubic feet per second and is scheduled to be complete in the summer of 2018.

“Vital infrastructure is a key focus for President Obama, the Department of the Interior and Reclamation and we’re proud of the monumental work being accomplished on this project by our employees, contractors and partners,” said Commissioner Estevan López. “These awards mark a significant milestone for the project; all Reclamation construction along the Cutter Lateral is now either underway or under contract and we’re on track to begin water deliveries through the lateral in 2019.” said Brent Rhees, Director of Reclamation’s Upper Colorado Region. The Navajo Nation is also moving forward with design and construction of downstream sections of the lateral under a financial assistance agreement with Reclamation.

The Navajo-Gallup Water Supply Project is the cornerstone of the San Juan River Basin in New Mexico Navajo Nation Water Rights Settlement Agreement. When complete, it will include approximately 300 miles of pipe, two water treatment plants, 19 pumping plants and multiple water storage tanks.

# # #

The Bureau of Reclamation is a federal agency under the U.S. Department of the Interior and is the nation's largest wholesale water supplier and second largest producer of hydroelectric power. Our facilities also provide substantial flood control, recreation opportunities, and environmental benefits. Visit our website at https://www.usbr.gov and follow us on Twitter @USBR; Facebook @bureau.of.reclamation; LinkedIn @Bureau of Reclamation; Instagram @bureau_of_reclamation; and YouTube @reclamation.