Colorado
Estes Powerplant
Generation by Unit (MW)
Unit 1: 0.0 MW
Unit 2: 15.0 MW
Unit 3: 14.9 MW
Nameplate Capacity: 45 MW
Total: 29.9 / 45.0 66.4%
Daily 131 MWh
Weekly 1158 MWh
Monthly 7714 MWh
as of 12/17/2025 07:00
Flatiron Powerplant
Generation by Unit (MW)
Unit 1: 43.0 MW
Unit 2: 0.0 MW
Unit 3: -9.0 MW
Nameplate Capacity: 94.5 MW
Big Thompson Powerplant
Unit 1: 0.0 MW
Nameplate Capacity: 4.5 MW
Total: 43.0 / 99.0 43.4%
Daily 221 MWh
Weekly 2153 MWh
Monthly 14567 MWh
as of 12/17/2025 07:00
Green Mountain Powerplant
Generation by Unit (MW)
Unit 1: 1.1 MW
Unit 2: 0.0 MW
Nameplate Capacity: 26 MW
Total: 1.1 / 26.0 4.2%
Daily 8 MWh
Weekly 57 MWh
Monthly 338 MWh
as of 12/17/2025 07:00
Marys Lake Powerplant
Generation by Unit (MW)
Unit 1: 8.6 MW
Nameplate Capacity: 8.1 MW
Total: 8.6 / 8.1 106.2%
Daily 69 MWh
Weekly 407 MWh
Monthly 3033 MWh
as of 12/17/2025 07:00
Mount Elbert Powerplant
Generation by Unit (MW)
Unit 1: -0.2 MW
Unit 2: 0.1 MW
Nameplate Capacity: 200 MW
Total: 0.1 / 200.0 0.1%
Daily 0 MWh
Weekly 69 MWh
Monthly 533 MWh
as of 12/17/2025 07:00
Pole Hill Powerplant
Generation by Unit (MW)
Unit 1: 32.6 MW
Nameplate Capacity: 38.238 MW
Total: 32.6 / 38.238 85.3%
Daily 262 MWh
Weekly 1831 MWh
Monthly 11863 MWh
as of 12/17/2025 07:00
Montana
Canyon Ferry Powerplant
Generation by Unit (MW)
Unit 1: 15.6 MW
Unit 2: 15.4 MW
Unit 3: 0.0 MW
Nameplate Capacity: 50 MW
Total: 31.0 / 50.0 62.0%
Daily 217 MWh
Weekly 1591 MWh
Monthly 7804 MWh
as of 12/17/2025 07:00
Yellowtail Powerplant
Generation by Unit (MW)
Unit 1: 48.3 MW
Unit 2: 0.0 MW
Unit 3: 0.0 MW
Unit 4: 56.8 MW
Nameplate Capacity: 250 MW
Total: 105.1 / 250.0 42.0%
Daily 431 MWh
Weekly 3796 MWh
Monthly 26732 MWh
as of 12/17/2025 07:00
Wyoming
Alcova Powerplant
Generation by Unit (MW)
Unit 1: 0.0 MW
Unit 2: 4.5 MW
Nameplate Capacity: 41.4 MW
Total: 4.5 / 41.4 10.9%
Daily 31 MWh
Weekly 221 MWh
Monthly 1648 MWh
as of 12/17/2025 07:00
Boysen Powerplant
Generation by Unit (MW)
Unit 1: 3.8 MW
Unit 2: 0.0 MW
Nameplate Capacity: 15 MW
Total: 3.8 / 15.0 25.3%
Daily 26 MWh
Weekly 220 MWh
Monthly 1577 MWh
as of 12/17/2025 07:00
Buffalo Bill Powerplant
Generation by Unit (MW)
Unit 1: 0.0 MW
Unit 2: 0.0 MW
Unit 3: 0.0 MW
Nameplate Capacity: 18 MW
Shoshone Powerplant
Unit 3: 1.8 MW
Nameplate Capacity: 3 MW
Spirit Mountain Powerplant
Unit 1: 0.0 MW
Nameplate Capacity: 4.5 MW
Heart Mountain Powerplant
Unit 1: 0.0 MW
Nameplate Capacity: 5 MW
Total: 1.8 / 30.5 5.9%
Daily 13 MWh
Weekly 99 MWh
Monthly 688 MWh
as of 12/17/2025 07:00
Fremont Powerplant
Generation by Unit (MW)
Unit 1: 0.3 MW
Unit 2: 0.0 MW
Nameplate Capacity: 66.8 MW
Total: 0.3 / 66.8 0.4%
Daily 0 MWh
Weekly 453 MWh
Monthly 3816 MWh
as of 12/17/2025 07:00
Glendo Powerplant
Generation by Unit (MW)
Unit 1: 0.0 MW
Unit 2: 0.0 MW
Nameplate Capacity: 38 MW
Total: 0.0 / 38.0 0.0%
Daily 0 MWh
Weekly 0 MWh
Monthly 0 MWh
as of 12/17/2025 07:00
Guernsey Powerplant
Generation by Unit (MW)
Unit 1: 0.0 MW
Unit 2: 0.0 MW
Nameplate Capacity: 6.4 MW
Total: 0.0 / 6.4 0.0%
Daily 0 MWh
Weekly 0 MWh
Monthly 0 MWh
as of 12/17/2025 07:00
Kortes Powerplant
Generation by Unit (MW)
Unit 1: 0.1 MW
Unit 2: 7.1 MW
Unit 3: 0.0 MW
Nameplate Capacity: 36 MW
Total: 7.2 / 36.0 20.0%
Daily 51 MWh
Weekly 407 MWh
Monthly 2785 MWh
as of 12/17/2025 07:00
Seminoe Powerplant
Generation by Unit (MW)
Unit 1: 5.5 MW
Unit 2: 0.0 MW
Unit 3: 0.0 MW
Nameplate Capacity: 51.75 MW
Total: 5.5 / 51.75 10.6%
Daily 37 MWh
Weekly 295 MWh
Monthly 1940 MWh
as of 12/17/2025 07:00