Colorado

 Estes Powerplant 
 Generation by Unit (MW) 
 Unit 1: 14.9 MW 
 Unit 2: 0.0 MW 
 Unit 3: 14.9 MW 
 Nameplate Capacity: 45 MW 
 Total: 29.8 / 45.0 66.2% 
 Daily 334 MWh 
 Weekly 834 MWh 
 Monthly 8399 MWh 
 as of 02/17/2026 17:00 

 Flatiron Powerplant 
 Generation by Unit (MW) 
 Unit 1: 13.1 MW 
 Unit 2: 30.7 MW 
 Unit 3: -8.4 MW 
 Nameplate Capacity: 94.5 MW 
 Big Thompson Powerplant 
 Unit 1: 0.0 MW 
 Nameplate Capacity: 4.5 MW 
 Total: 43.8 / 99.0 44.2% 
 Daily 599 MWh 
 Weekly 1579 MWh 
 Monthly 16069 MWh 
 as of 02/17/2026 17:00 

 Green Mountain Powerplant 
 Generation by Unit (MW) 
 Unit 1: 1.2 MW 
 Unit 2: 0.0 MW 
 Nameplate Capacity: 26 MW 
 Total: 1.2 / 26.0 4.6% 
 Daily 19 MWh 
 Weekly 45 MWh 
 Monthly 484 MWh 
 as of 02/17/2026 17:00 

 Marys Lake Powerplant 
 Generation by Unit (MW) 
 Unit 1: 8.3 MW 
 Nameplate Capacity: 8.1 MW 
 Total: 8.3 / 8.1 102.5% 
 Daily 153 MWh 
 Weekly 359 MWh 
 Monthly 3460 MWh 
 as of 02/17/2026 17:00 

 Mount Elbert Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.5 MW 
 Unit 2: 0.1 MW 
 Nameplate Capacity: 200 MW 
 Total: 0.6 / 200.0 0.3% 
 Daily 0 MWh 
 Weekly 0 MWh 
 Monthly 2063 MWh 
 as of 02/17/2026 17:00 

 Pole Hill Powerplant 
 Generation by Unit (MW) 
 Unit 1: 32.5 MW 
 Nameplate Capacity: 38.238 MW 
 Total: 32.5 / 38.238 85.0% 
 Daily 591 MWh 
 Weekly 1380 MWh 
 Monthly 13159 MWh 
 as of 02/17/2026 17:00 

Montana

 Canyon Ferry Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.0 MW 
 Unit 2: 18.3 MW 
 Unit 3: 18.1 MW 
 Nameplate Capacity: 50 MW 
 Total: 36.4 / 50.0 72.8% 
 Daily 618 MWh 
 Weekly 1468 MWh 
 Monthly 13781 MWh 
 as of 02/17/2026 17:00 

 Yellowtail Powerplant 
 Generation by Unit (MW) 
 Unit 1: 52.8 MW 
 Unit 2: 0.0 MW 
 Unit 3: 0.0 MW 
 Unit 4: 25.5 MW 
 Nameplate Capacity: 250 MW 
 Total: 78.3 / 250.0 31.3% 
 Daily 996 MWh 
 Weekly 2533 MWh 
 Monthly 25127 MWh 
 as of 02/17/2026 17:00 

Wyoming

 Alcova Powerplant 
 Generation by Unit (MW) 
 Unit 1: 4.5 MW 
 Unit 2: 0.0 MW 
 Nameplate Capacity: 41.4 MW 
 Total: 4.5 / 41.4 10.9% 
 Daily 74 MWh 
 Weekly 180 MWh 
 Monthly 1773 MWh 
 as of 02/17/2026 17:00 

 Boysen Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.0 MW 
 Unit 2: 0.0 MW 
 Nameplate Capacity: 15 MW 
 Total: 0.0 / 15.0 0.0% 
 Daily 0 MWh 
 Weekly 0 MWh 
 Monthly 0 MWh 
 as of 02/17/2026 17:00 

 Buffalo Bill Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.0 MW 
 Unit 2: 0.0 MW 
 Unit 3: 0.0 MW 
 Nameplate Capacity: 18 MW 
 Shoshone Powerplant 
 Unit 3: 1.7 MW 
 Nameplate Capacity: 3 MW 
 Spirit Mountain Powerplant 
 Unit 1: 0.0 MW 
 Nameplate Capacity: 4.5 MW 
 Heart Mountain Powerplant 
 Unit 1: 0.0 MW 
 Nameplate Capacity: 5 MW 
 Total: 1.7 / 30.5 5.6% 
 Daily 29 MWh 
 Weekly 71 MWh 
 Monthly 785 MWh 
 as of 02/17/2026 17:00 

 Fremont Powerplant 
 Generation by Unit (MW) 
 Unit 1: 29.7 MW 
 Unit 2: -0.1 MW 
 Nameplate Capacity: 66.8 MW 
 Total: 29.7 / 66.8 44.5% 
 Daily 61 MWh 
 Weekly 275 MWh 
 Monthly 3499 MWh 
 as of 02/17/2026 17:00 

 Glendo Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.0 MW 
 Unit 2: 0.0 MW 
 Nameplate Capacity: 38 MW 
 Total: 0.0 / 38.0 0.0% 
 Daily 0 MWh 
 Weekly 0 MWh 
 Monthly 0 MWh 
 as of 02/17/2026 17:00 

 Guernsey Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.0 MW 
 Unit 2: 0.0 MW 
 Nameplate Capacity: 6.4 MW 
 Total: 0.0 / 6.4 0.0% 
 Daily 0 MWh 
 Weekly 0 MWh 
 Monthly 0 MWh 
 as of 02/17/2026 17:00 

 Kortes Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.1 MW 
 Unit 2: 7.1 MW 
 Unit 3: 0.0 MW 
 Nameplate Capacity: 36 MW 
 Total: 7.2 / 36.0 20.0% 
 Daily 124 MWh 
 Weekly 298 MWh 
 Monthly 2894 MWh 
 as of 02/17/2026 17:00 

 Seminoe Powerplant 
 Generation by Unit (MW) 
 Unit 1: 0.0 MW 
 Unit 2: 5.2 MW 
 Unit 3: 0.0 MW 
 Nameplate Capacity: 51.75 MW 
 Total: 5.2 / 51.75 10.0% 
 Daily 84 MWh 
 Weekly 203 MWh 
 Monthly 2038 MWh 
 as of 02/17/2026 17:00