| Contract No. 99-CC-40-2180 Blanco Diversion Dam Sluiceway Repair and Willow Structure Repair, San Juan-Chama Project, Colorado |
|
| Contract Specialist | Evelyn Doussard (801) 524-3645 |
| Contracting Officer | Richard Kerr |
| Awarded | 08/20/99 |
| Amount | $707,314.59 / step 2 |
| To | AJAC Enterprises Inc. |
| Contract No. 99-CC-40-2400 Rehabilitate Pumping Plant G13.3L Near Farmington, New Mexico |
|
| Contract Specialist | Tom Walsh (801) 524-3760 |
| Contracting Officer | Richard Kerr |
| Awarded | 08/18/99 |
| Amount | $1,494,391.00 |
| To | JAMCO Constructors NM, Inc. |
| Contract No. 99-CC-40-2560 Chip and Seal Crystal and Morrow Point Roads, Wayne Aspinall Unit, CRSP - Colorado |
|
| Contract Specialist | Tom Walsh (801) 524-3760 |
| Contracting Officer | Richard Kerr |
| Awarded | 07/23/99 |
| Amount | $300,840.00 |
| To | GMCO LLC |
| Contract No. 99-CA-40-1480 Expert Witness Services, Marshall and Associated Contractors Claim |
|
| Contract Specialist | Mike Ward (801) 524-3761 |
| Contracting Officer | Mike Ward |
| Awarded | 05/18/99 |
| Amount | $30,000.00 / phase 1 (ceiling amount of $250,000.00 for all 5 phases) |
| To | A.W. Hutchison and Associates Inc. |
| Contract No. 99-CC-40-1680 Generator Switchgear Assemblies, Glen Canyon Power Plant - Page, Arizona |
|
| Contract Specialist | Barbara Taylor (801) 524-3750 |
| Contracting Officer | Mike Ward |
| Awarded | 04/05/99 |
| Amount | $4,826,494.00 |
| To | Gardner Zemke Compke |
| Contract No. 99-CC-40-1590 Wahweap Fish Hatchery - Phase IV Rearing Pond Kettles and Access Ramps, Big Water, Utah |
|
| Contract Specialist | William Hermann (801) 524-3665 |
| Contracting Officer | Brent Rhees |
| Awarded | 03/31/99 |
| Amount | $141,396.78 |
| To | Spectrum Construction of Utah |
| Contract No. 99-PG-40-1550 24 Road Fish Hatchery Addition, Grand Junction, Colorado |
|
| Contract Specialist | William Hermann (801) 524-3665 |
| Contracting Officer | Pat Martinez |
| Awarded | 02/09/99 |
| Amount | $145,000.00 |
| To | ALCO Building Company Inc. |
| Contract No. 99-CC-40-101A Acequia Improvements, Phase IV, Velarde Community Ditch Project, NM |
|
| Contract Specialist | Carleen Ashbaker (801) 524-3617 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/17/98 |
| Amount | $3,210,806.15 |
| To | AJAC Enterprises Inc. |
| Contract No. 99-CC-40-101B Acequia Improvements, Phase IV, Verlade Community Ditch Project |
|
| Contract Specialist | Carleen Ashbaker (801) 524-3617 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/17/98 |
| Amount | $3,686,555.15 |
| To | AMC Construction Inc. |
| Contract No. 99-CC-40-101c Acequia Improvements, Phase IV, Velarde Community Ditch Project, New Mexico |
|
| Contract Specialist | Carleen Ashbaker (801) 524-3617 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/17/98 |
| Amount | $3,814,769.95 |
| To | Cumbre Construction Inc. |
| Contract No. 99-CC-40-101D Acequia Improvements, Phase IV, Velarde Community Ditch Project, New Mexcio |
|
| Contract Specialist | Carleen Ashbaker (801) 524-3617 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/17/98 |
| Amount | $3,529,841.95 |
| To | M.R. Tafoya Construction Inc. |
| Contract No. 99-CC-40-101E Acequia Improvements, Phase IV Velarde Community Ditch Project, New Mexico |
|
| Contract Specialist | Carleen Ashbaker (801) 524-3617 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/14/98 |
| Amount | $4,287,884.16 |
| To | PMR Construction Services Inc. |
| Contract No. 99-CC-40-1360 Block 2, Subsurface Test Drains - Navajo Indian Irrigation Project, New Mexico |
|
| Contract Specialist | Barbara Taylor (801) 524-3750 |
| Contracting Officer | William Hermann |
| Awarded | 12/11/98 |
| Amount | $397,683.00 |
| To | John M. Keltch Inc. |
| Contract No. 99-CC-49-1360 Deer Creek State Park Facility Improvements - Phase 2, Provo Project, Utah |
|
| Contract Specialist | Tom Walsh (801) 524-3760 |
| Contracting Officer | Richard Kerr |
| Awarded | 10/21/98 |
| Amount | $12,215,676.00 |
| To | Herm Hughes & Sons Inc. |
| Contract No. 99-CA-40-1480 Expert Witness Services, Marshall and Associated Contractors Claim |
|
| Contract Specialist | William Herman (801) 524-3665 |
| Contracting Officer | Mike Ward |
| Awarded | 05/18/99 |
| Amount | $30,000.00 (phase 1) |
| To | A.W. Hutchison and Associates Inc. |
| Contract No. 99-PG-40-1550 24 Road Fish Hatchery Addition, Grand Junction, Colorado |
|
| Contract Specialist | William Herman (801) 524-3665 |
| Contracting Officer | Mike Ward |
| Awarded | 02/09/99 |
| Amount | $145,000.00 |
| To | ALCO Building Company |
| Contract No. 99-CA-40-0270 A&E Resource Management Plans, Upper Colorado Region |
|
| Contract Specialist | Evelyn Doussard (801) 524-3645 |
| Contracting Officer | Mike Ward |
| Awarded | 01/19/99 |
| Amount | $2,476,000.00 |
| To | Bio/West Inc. |
| Contract No. 99-CS-40-0930 Generator Circuit Breaker Replacement, Morrow Point Powerplant |
|
| Contract Specialist | Carleen Ashbaker (801) 524-3617 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/18/98 |
| Amount | $1,069,000.00 |
| To | Wesco Distribution Inc. |
| Contract No. 99-CS-40-0250 Surveying Services, Upper Colorado Region |
|
| Contract Specialist | Evelyn Doussard (801) 524-3645 |
| Contracting Officer | Mike Ward |
| Awarded | 11/12/98 |
| Amount | $2,609,900.00 |
| To | Surveying Services |
| Contract No. 99-CS-40-1410 Station Service Transformers For Morrow Point and Crystal Powerplant, Montrose Colorado |
|
| Contract Specialist | Janet Johnson (801) 524-3613 |
| Contracting Officer | Gary McDermott |
| Awarded | 03/08/99 |
| Amount | $60,690.00 |
| To | Power Engineering Corp. |
| Contract No. 99-CP-40-0940 Replacement Runner For Impulse-Type Hydraulic Turbine At Upper Molina Powerplant, Collbran Project |
|
| Contract Specialist | Tom Walsh (801) 524-3760 |
| Contracting Officer | Richard Kerr |
| Awarded | 12/10/98 |
| Amount | $343,675.00 |
| To | IMPSA International Inc. |