Bureau of Reclamation Banner
Reclamation Home             Reclamation Offices             Newsroom             Library             Projects & Facilities
Home > Third Power Plant > Overhaul Project > Project Summary
Third Power Plant Overhaul Project
Project Summary

This project will involve overhauling turbines G-19 through G-24 in the Third Powerplant. The units have been in service since the mid-1970s and have been heavily used over the years. Their condition has deteriorated to the point that complete overhaul is necessary to ensure these machines will continue to operate reliably. Work will be performed on generators, turbines, shafts, and auxiliary equipment with the overall goal of ensuring another 30 years of dependable service.

Units G-19 through G-21 are equipped with 820,000-horsepower Francis turbines, designed by Dominion Engineering Works, Ltd., and manufactured by Willamette Iron and Steel Company with a runner throat diameter of 34 feet. Units G-22 through G-24 are equipped with 960,000-HP Francis turbines, designed and manufactured by Allis-Chalmers with a runner throat diameter of 32 feet.

Generators G-22, G-23, and G-24 are rated to produce a total of 2,415 Mega-Volt-Amps (MVA) with an annual power production value of over $100 million. The units have begun to show age-related component wear. These units will be overhauled first because they are in worse general condition than units G19-G21. The work will include inspecting, refurbishing or replacing worn mechanical and electrical components, including bushings, seals, controls, and deteriorated wiring. Stator cores or windings for Units G-22, G-23, and G-24 were replaced recently and should not need attention beyond inspection and cleaning. Rotor will be inspected and repaired as needed.

Units G-19, G-20, and G-21 may be up-rated in overall unit capacity with new generator and turbine components. Collectively, these three smaller units provide 1,845 MVA (615 MVA each).  A recent study has shown that the Third Power Plant (TPP) G19-G21 Generator windings, generator shaft, and turbine runners will need to be replaced in order to achieve uprate to 790 MVA each; power officials are looking at cost-benefits that consider both uprate value and reduction of triennial cavitation repair to determine if this investment is economically justifiable.

Reclamation is preparing for the overhaul outages by identifying specific repair needs, performing detailed analysis, performing design work, and seeking contracts for work to be completed prior to overhaul. A considerable amount of the Planning and Design work is being accomplished in partnership with Architect-Engineering companies under contract with Reclamation. These efforts will result in improved reliability of equipment that is needed to support the overhaul, will identify ways to minimize outage durations, and will reduce the likelihood and magnitude of increases to outage time.

In accomplishing the overhaul a large amount of lay-down space is required for all turbine and generator parts as they are removed. More space is required during the overhauls than for initial construction when parts were delivered as needed. Each unit has several large and heavy items that require special consideration:

  • Upper bracket (diameter approximately 83 feet)
  • Rotor (diameter approximately 58 feet)
  • Main support bracket (diameter approximately 45 feet)
  • Head cover (diameter approximately 35 feet)
  • Operating ring (diameter approximately 25 feet)
  • Three main shaft sections which must be stored in a vertical position

It is expected that these large parts will occupy most of the TPP floor space except for access aisles needed to move smaller components.

In order to refurbish the existing parts, a temporary machine shop and paint booth buildings have been erected adjacent to the TPP.   
 
Contacts
Brian Clark
bdclark@usbr.gov
Project Manager
Grand Coulee Power Office
(509) 633-9693
Contact Us | Maps | Lake Level | News & Photos | A-Z Index | Laser Show | FAQ Bureau of Reclamation Facebook Bureau of Reclamation RSS Feed Bureau of Reclamation YouTube Bureau of Reclamation Twitter
Pacific Northwest Region RSS Feed Bureau of Reclamation YouTube Page Bureau of Reclamation Twitter Page

Last Update: October 18, 2006 1:11 PM