Bureau of Reclamation Banner
Reclamation Home             Reclamation Offices             Newsroom             Library             Projects & Facilities

Grand Coulee Dam: Third Powerplant Overhaul Project

Introduction

Installing turbine blades at Grand Coulee Dam’s Third Powerplant. December 1974.The six generating units in the Third Powerplant (TPP) have been in service since the mid-1970s. Age-related wear is beginning to create problems problems which have resulted in increased power outages and reduced reliability. The overhaul project will ensure continued operation of the powerplant and allow Reclamation to provide a reliable source of hydroelectric power to the region.

Reclamation is preparing for the overhaul outages by identifying specific repair needs, performing detailed analysis, performing design work, and seeking contracts for work to be completed prior to overhaul. A considerable amount of the Planning and Design work is being accomplished in partnership with Architect-Engineering companies under contract with Reclamation.

These efforts will result in improved reliability of equipment that is needed to support the overhaul, will identify ways to minimize outage durations, and will reduce the likelihood and magnitude of increases to outage time.

Project Summary
Projects to be Completed Prior to the Overhaul
Other Third Powerplant Overhaul-Related Projects
Photo Gallery
Third Powerplant Generating Units Overhaul Activities Draft Environmental Assessment

Project Update

Third Power Plant Status Report – September 22, 2009

TPP Overhaul: Review of the 90% procurement package for the overhaul contract has been completed.   The Architect-Engineer firm “MWH Americas” was hired to study key overhaul efforts and make recommendations to reduce risks associated with them.  We will receive their 90% product in October and role that information into the final procurement package.  We are on track to advertise this spring. 
A General Engineer was hired for the project.

Material Storage Building (MSB):  Reclamation is preparing for the EA. Three alternatives will be included in the EA.  Reclamation’s preferred alternative is for a separate MSB and no extension of the TPP.

NEPA for MSB and TPP Overhaul:   A draft EA is scheduled to be issued for public review on Oct. 6, 2009.

TPP Cranes: A preliminary design was completed.  65% design review will be September 26, 2009.

Fixed Wheel Gate Chamber Modifications: Tribal comment on historical impacts has been requested.  Comments are due by October 13, 2009. 

TPP Elevators: An award for preliminary design (phase 1); and, completion of both the design and the procurement package (phase 2) was awarded. The initial contractor completed phase 1, but is unable to deliver on phase 2.   CH2MHill will provide new design and complete phase 2.

Excitation System: Solicitation for contract complete. Contract is expected to be awarded in November 2009.

Governor Upgrades: In contracting awaiting funding approval. 

Transformer Replacement (G19 & G20): Solicitation for contract complete. Contract is expected to be awarded in November 2009.

500 KV Cable:  EA comment period ended September 15, 2009. Comments are being evaluated.  BPA will complete LIDAR topography flight before October 5, 2009.  NEPA and design continue.

Shaft Seals: Solicitation went out on September 11, 2009.

rule
Tentative Schedule

Activity

Start

Finish

Overhaul Units G22-24

April 2008

September 2017

  Design

March 2009

January 2010

  Contracting

January 2010

August 2011

  Construction

August 2011

September 2017

     Plan, Design, Procure, Site Prep

August 2011

June 2013

     Overhaul G-24

March 2013

September 2014

     Overhaul G-23

September 2014

March 2016

     Overhaul G-22

March 2016

September 2017

 

 

 

Overhaul Units G19-G21

To be determined

To be determined

 

 

 

New Material Storage Bldg

June 2008

December 2012

TPP Elevators

June 2008

September 2012

Modify Fixed-Wheel Gate Chamber

June 2008

July 2011

Rehab TPP Cranes

June 2008

February 2013

New TPP Exciters

May 2007

October 2014

New TPP Governor Controls

September 2008

October 2014

Replace 236MVA Transformers

November 2006

November 2012

New 500KV Cables

February 2009

December 2011

News Releases

 

03/04/2009 Reclamation Awards $2 Million Contract for Grand Coulee Third Powerplant Project Planning
02/27/2009

Reclamation Prepares EA on Proposed Grand Coulee Third Powerplant Overhaul

Contacts

Lynne Brougher
lbrougher@usbr.gov
Public Affairs Officer
Grand Coulee Power Office
(509) 633-9503
Scott Ross
sross@usbr.gov
Project Manager
Grand Coulee Power Office
(509) 633-9322
 

Last Update: November 4, 2009 3:50 PM