Reclamation Acquisition Regulations (RAR)

PART WBR 1449

TERMINATION OF CONTRACTS

LAST UPDATED: ET 00-01, SUPPLEMENT 1 (3/8/00)


TABLE OF CONTENTS

SUBPART WBR 1449.1 GENERAL PRINCIPLES

WBR 1449.101 Authorities and responsibilities.
WBR 1449.107 Audit of prime contract settlement proposals and subcontract settlements.

SUBPART WBR 1449.3 -- ADDITIONAL PRINCIPLES FOR COST REIMBURSEMENT CONTRACTS TERMINATED FOR CONVENIENCE

WBR 1449.303 Procedure after discontinuing vouchers.
WBR 1449.303-3 Audit of settlement proposal.

SUBPART WBR 1449.4 -- TERMINATION FOR DEFAULT

WBR 1449.402 Termination of fixed-price contracts for default.
WBR 1449.402-6 Repurchase against contractor's account.


PART WBR 1449
TERMINATION OF CONTRACTS

SUBPART 1449.1 -- GENERAL PRINCIPLES

 

WBR 1449.101 Authorities and responsibilities. In addition to the responsibilities listed in FAR 49.101(b) , the CO shall also prepare a memorandum for the contract file explaining the reasons for the termination for convenience.

WBR 1449.107 Audit of prime contract settlement proposals and subcontract settlements. Responses to audit reports shall be made in accordance with WBR 1401.7081-3(b) .


SUBPART WBR 1449.3

ADDITIONAL PRINCIPLES FOR COST-REIMBURSEMENT

CONTRACTS TERMINATED FOR CONVENIENCE

 

WBR 1449.303 Procedure after discontinuing vouchers.

WBR 1449.303-3 Audit of settlement proposal. Responses to audit reports shall be made in accordance with WBR 1401.7081-3(b) .


SUBPART WBR 1449.4 -- TERMINATION FOR DEFAULT

WBR 1449.402 Termination of fixed-price contracts for default.

WBR 1449.402-6 Repurchase against contractor's account.

Repurchase of undelivered quantities terminated for default shall include any prepriced options which were entitled to be exercised.