Reclamation Acquisition Regulations (RAR)
PART WBR 1443
CONTRACT MODIFICATIONS
SUBPART WBR 1443.1 -- GENERAL
WBR 1443.102 Policy.
WBR 1443.102-80 New work under current contracts.
WBR 1443.107 Contract
clause.
WBR 1443.107-80
Reclamation contract clause.
SUBPART WBR 1443.2 -- CHANGE ORDERS
SUBPART WBR 1443.3 -- FORMS
PART WBR 1443 -- CONTRACT MODIFICATIONS
SUBPART WBR 1443.1--GENERAL
SUBPART WBR 1443.1--GENERAL
(a) Reclamation's ability to negotiate an equitable adjustment resulting from a change order decreases as the work required by the change order is completed by the contractor. As a best business practice, modifications shall be forward priced and issued as supplemental agreements in accordance with FAR 43.102(b) unless the CO justifies in writing the reasons for not issuing a supplemental agreement. In such an instance, the justification shall be prepared at the time the change order is issued, and shall --
(1) Identify the work required by the change, the estimated cost of the change, and the specific circumstance(s) which preclude negotiation of the equitable adjustment prior to commencement of work;
(2) Discuss the a maximum price limitation negotiated for the work and to be included in the change order or state the reasons why negotiation is impracticable and the measures taken to limit the Government's liability; and
(3) Discuss the schedule for definitization and the date the work is to expected to be completed to insure that the equitable adjustment is negotiated in the shortest practicable time as required by FAR 43.204(b) .
WBR 1443.102-80 New work under current contracts. Work outside of the general scope of the contract may be added to an existing contract provided that --
(a) It is not added using the authority of the "Changes" clause; and
(b) It is treated as new work and is justified and approved under FAR 6.302 , DIAR Part 1406 and WBR Part 1406 .
WBR 1443.107-80 Reclamation contract clause.
The CO shall insert the clause at WBR 1452.243-80 , Modification Proposals -- Bureau of Reclamation, in all solicitations and contracts except for acquisitions for commercial items. If limitations are to be placed on the contractor's indirect cost applied to work performed by subcontractors or suppliers, the CO shall use the clause with its Alternate I. When the Change Order Accounting clause is included in the contract, the CO shall use the Modification Proposals clause with its Alternate II. When the Equipment Ownership and Operating Expense clause is included in the contract, the CO shall use the Modification Proposals clause with its Alternate III. When both the Change Order Accounting and the Equipment Ownership and Operating Expense clauses are included in the contract, the CO shall use the Modification Proposals clause with its Alternate IV.
SUBPART WBR 1443.2--CHANGE ORDERS
(a) Change order documentation. Before issuing a change order which is not forward priced, the justification required by WBR 1443.102 shall be prepared and signed by the CO.
(b) Definitization.
(1) After issuance of a change order, the CO shall, where possible, establish a suspense date for prompt definitization of the order after discussing with the contractor the due date for submission of the equitable adjustment proposal.
(2) If a proposal is not received by the due date, the CO shall contact the contractor to determine the cause for the delay. The due date may be extended by the CO based on the circumstances involved in preparing the proposal but in no event may this date be later than the date estimated for completion of the work, unless performance is completed prior to 30 days after receipt of the change order.
(3) If a proposal is not received by the due date, or subsequent date extended by the CO, the CO may issue a unilateral equitable adjustment of the contract pursuant to the Changes clause of the contract.
(4) In determining the amount of profit associated with the equitable adjustment, the CO shall consider the amount of work already performed by the date of the negotiation and any associated decrease in the contractor's cost risk.
(c) Complete and final equitable adjustment. In lieu of the suggested language in FAR 43.204(c)(2) a release, substantially as follows, shall be included in every supplemental agreement issued or the CO shall document the contract file with the reasons for altering the release language or for omitting it altogether. This does not preclude the CO from using more detailed release language recommended by the Office of the Solicitor for specific actions.
CONTRACTOR'S STATEMENT OF RELEASE.
The contractor hereby accepts the adjustments in the contract price and/or contract performance period set forth in this Supplemental Agreement No._________ to Contract No._________, as the complete, equitable and final adjustment for the changed requirements/conditions authorized herein and agrees that the Government has no further liability whatsoever, directly or indirectly, in regard to any claims, known or unknown, including claims for delay and/or disruption, for any additional adjustments to the contract by reason of these changed requirements/conditions.
SUBPART WBR 1443.3 -- FORMS
(a) Purchase order modifications.
(1) Standard form 30 (SF-30), Amendment of Solicitation/Modification of Contract, shall be used for purchase order modifications as prescribed in WBR 1413.302-3 and in accordance with the procedures in FAR 43.103.
(2) The instructions provided on the reverse side of the SF-30 as supplemented below shall be used for completion of the SF-30 when issuing modifications to purchase orders.
(i) Unilateral modifications. CO's shall complete block 13A of the SF-30 citing an appropriate authority to reflect the issuance of an authorized unilateral modification.
(ii) Bilateral modifications. CO's shall complete block 13C citing the appropriate authority for issuing a bilateral modification (supplemental agreement). If the purchase order does not have an appropriate clause which authorizes the modification, the CO may cite "By mutual agreement of the parties." When a SF-30 is used to bilaterally modify a FSS delivery order, the citation authority should be cited as "terms of GSA Contract No.________."
(3) Documentation.
(i) Purchase order modifications not greater than $25,000 may
be documented using Reclamation form 7-2080 (illustrated in WBR 1453.303-2080).
(ii)
Purchase order modifications greater than $25,000 shall be documented
using Reclamation form 1453.303-1413-1
. Contracting officers may use this format for purchase order
modifications which do not exceed $25,000 as they deem appropriate.