2002
Study Started (August)
2003
Public Involvement Plan (March)
2003
Interim Report (June)
2003
NOI/NOP (July/August)
2003
Scoping Meetings (September)
2004
Scoping Report (March)
2004
Draft Initial Alternatives Report (May)
2005
Initial Alternatives Report (March)
2005
Draft Biological Assessment (December)
2006
Biological Assessment (February)
2006
Draft Feasibility Report / EIS/EIR (July)
2006
Public Hearing (October)
2006
Final Feasibility Report / EIS/EIR (December)
2007
Record of Decision (January)