Drop 2 Storage Reservoir Project
Project Milestones/Schedule
| May 2004 |
Value Planning Study |
| February 2005 |
Appraisal and Storage Alternatives Study |
| March 2006 |
Value Engineering Study |
| November 2006 |
Draft Environmental Assessment |
| March 2007 |
Feasibility Design Report |
| July 2007 |
Final Environmental Assessment |
| November 2007 |
Environmental Determination Document |
| March 2007 through March 2008 |
Final Design Period |
| December 2007 |
Funding Agreement |
| August 2008 |
Operations Agreement |
| September 2008 through October 2010 |
Construction Period |
| Ongoing |
Stakeholder Coordination; Environmental, Cultural and Lands Compliance; Project Management |
|