Functional Area: Engineering and Design Services
*The following items will be addressed by one team.
Action Item 14*
Implement design engineering estimate oversight functions associated with the Design Engineering Construction (DEC)/Dam Safety Officer (DSO) position; identify and conduct pilot reviews of key project feature construction estimates during FY 2006.Action Item 15*
Establish agency policies and procedures for the oversight of design and construction estimates.Team Lead: Perry Hensley, DEC/DSO Senior Advisor, Office of Technical Resources
Objective:
- Establish the Dam Safety Officer (DSO) and the Design, Estimating and Construction Oversight Office Manager (DEC) position, and conduct pilot reviews of key project feature construction estimates.
- Establish agency policies and procedures for the oversight of design and construction estimates.
Tasks:
- Issue call letter for FY07-09 for DEC reviews.
- Issue temporary policy and Directives and Standards for DEC and Estimating.
- Conduct pilot reviews on Auburn Dam Update, TCD Glen Canyon Dam and the Reservoirs along the All American Canal (AAC) in FY06.
- Compile and prioritize DEC reviews for FY07-09.
Milestones:
- May 2006: Call letter issued to all Regions asking for lists of projects for FY07-09 that meet DEC review requirements.
- June 2006: Complete pilot review of Auburn Dam Update.
- July 2006: Complete pilot review of TCD Glen Canyon Dam.
- Aug. 2006: Issue Policy, Directives and Standards for DEC and Estimating.
- Aug. 2006: Complete report to Commissioner prioritizing & recommending DEC reviews in FY 07, 08 & 09 and reviews.
- Sept. 2006: Issue pilot review of AAC Reservoirs.
Products: (If you would like to provide comments on any draft products, visit the Draft Products page.)
No products available at this time.
Last Updated:
March 21, 2008