CVP - San Felipe Division - Main Page
Facilities in Operation
|
Storage Dams |
1 |
|
Pipelines |
56.6 mi |
|
Pumping Plants |
2 |
|
Storage Facilities
San Justo Dam
Carriage Facilities
Hollister Conduit
|
Location |
From the Pacheco Conduit to the San Justo Reservoir |
|
Construction period |
Section 1 - 1.7 miles completed. Section 2 - Proposed for 850 calendar days. |
|
Length |
19.5 mi |
|
Capacity |
83 cfs |
|
Pacheco Conduit
|
Location |
From Pacheco tunnel outlet to bifurication of Santa Clara and Hollister Conduits. |
|
Construction period |
Section 1 - Proposed for 760 calendar days. Section 2 - Proposed for 1,040 calendar days. |
|
Length |
7.9 mi |
|
Capacity |
480 cfs |
|
Pacheco Tunnel
|
Location |
From San Luis Reservoir through the Diablo Mountain Range. |
|
Construction period |
First 1.8 miles completed in 1968 5.3 miles under construction. |
|
Length |
7.1 mi |
|
Capacity |
480 cfs |
|
Cross section: |
Circular |
|
Diameter |
9.5 ft |
|
Lining type: |
Concrete |
|
Lining thickness |
8-18 in |
|
Santa Clara Tunnel and Conduit
|
Location |
From Pachco Conduit to Coyote Pumping Plant. |
|
Construction period |
Section 1 - Proposed for 810 calendar days. Section 2 - Proposed for 1,490 calendar days. Tunnel - Under construction. |
|
Length |
22.1 mi |
|
Capacity |
330 cfs |
|
Pumping Plants
|
Designation |
Number of units |
Total capacity, cfs |
Total dynamic head, ft |
Total horsepower |
|
Pacheco |
12 |
504 |
306 |
24,000 |
|
Coyote |
6 |
342 |
230 |
12,000 |
|
|