 CVP - San Felipe Division 
 Engineering Data

CVP - San Felipe Division  -  Main Page

Facilities in Operation

Storage Dams

1      

Pipelines

56.6 mi  

Pumping Plants

2      


Storage Facilities

Carriage Facilities

Hollister Conduit

Location

From the Pacheco Conduit to the San Justo Reservoir

Construction period

Section 1 - 1.7 miles completed.
Section 2 - Proposed for 850 calendar days.

Length

19.5 mi  

Capacity

83 cfs  


Pacheco Conduit

Location

From Pacheco tunnel outlet to bifurication of Santa Clara and Hollister Conduits.

Construction period

Section 1 - Proposed for 760 calendar days.
Section 2 - Proposed for 1,040 calendar days. 

Length

7.9 mi  

Capacity

480 cfs  


Pacheco Tunnel

Location

From San Luis Reservoir through the Diablo Mountain Range.

Construction period

First 1.8 miles completed in 1968
5.3 miles under construction.

Length

7.1 mi  

Capacity

480 cfs  

Cross section:

Circular

   Diameter

9.5 ft  

   Lining type:

Concrete

   Lining thickness

8-18 in  


Santa Clara Tunnel and Conduit

Location

From Pachco Conduit to Coyote Pumping Plant.

Construction period

Section 1 - Proposed for 810 calendar days.
Section 2 - Proposed for 1,490 calendar days.
Tunnel - Under construction.

Length

22.1 mi  

Capacity

330 cfs  


Pumping Plants

Designation

Number of units

Total capacity, cfs

Total dynamic head, ft

Total horsepower

Pacheco

12

504

306

24,000

Coyote

  6

342

230

12,000

 