Facilities in Operation
|
Storage Dams |
2 |
|
Diversion Dams |
1 |
|
Canals |
100 mi |
|
Laterals |
300 mi |
|
Drains |
644 mi |
|
Powerplants |
1 |
|
Transmission Lines |
75.8 mi |
|
Substations |
3 |
|
Storage Facilities
Bull Lake Dam Pilot Butte Dam
Diversion Facilities
Carriage Facilities
Wyoming Canal
|
Location |
From Wind River Diversion Dam on Wind River, about 32 miles northwest of Riverton, Wyoming, generally northeast along northern edge of irrigated area |
|
Construction period |
1920-1951 |
|
Length |
62.4 mi |
|
Diversion capacity |
2,200 cfs |
|
Typical section in earth: |
|
|
Bottom width |
65 ft |
|
Side slopes |
1.5:1 |
|
Water depth |
10 ft |
|
Typical section, concrete lined: |
|
|
Bottom width |
12.5 ft |
|
Side slopes |
1.5:1 |
|
Water depth |
10 ft |
|
Lining thickness |
6 in |
|
Pilot Canal
|
Location |
From Pilot Butte Reservoir generally southeast along southern edge of irrigated area |
|
Construction period |
1926-1947 |
|
Length |
38.2 mi |
|
Diversion capacity |
1,000 cfs |
|
Typical section in earth: |
|
|
Bottom width |
30 ft |
|
Side slopes |
2:1 |
|
Water depth |
10 ft |
|
Typical section, lined with buried asphalt membrane: |
|
|
Bottom width |
30 ft |
|
Side slopes |
2:1 |
|
Water depth |
10 ft |
|
Power Facilities
Pilot Butte Powerplant
|