Norman Project - Main Page
Facilities in Operation
|
Storage Dams |
1 |
|
Pipelines |
30.5 mi |
|
Pumping Plants |
2 |
|
Storage Facilities
Norman Dam
Carriage Facilities
Norman Pipeline
|
Type |
Precast reinforced concrete pressure pipe and cylinder pre-stressed concrete pipe |
|
Length |
8.2 mi |
|
Diameter |
33 and 30 in |
|
Capacity |
21.8 cfs |
|
Midwest City Pipeline
|
Type |
Precast reinforced concrete pressure pipe and cylinder pre-stressed concrete pipe |
| |
|
|
Length |
12.4 mi |
|
Diameter |
36, 33, and 30 in |
|
Capacity |
28.0 cfs |
| |
|
|
Length |
3.6 mi |
|
Diameter |
30 in |
|
Capacity |
20.1 cfs |
|
Del City Pipeline
|
Type |
Precast reinforced concrete pressure pipe and cylinder pre-stressed concrete pipe |
| |
|
|
Length |
6.3 mi |
|
Diameter |
21 and 18 in |
|
Capacity |
7.9 cfs |
|
Pumping Plants
|
Designation |
Number of units |
Total capacity, cfs |
Total dynamic head, ft |
Total horsepower |
|
Reservoir1 |
|
|
|
|
| |
4 |
22.9 |
320 |
800 |
| |
4 |
29.4 |
228 |
1,400 |
|
Relift1 |
|
|
|
|
| |
4 |
21.1 |
138 |
400 |
| |
2 |
5.0 |
104 |
80 |
| |
2 |
3.3 |
104 |
50 |
|
1 Reservoir plant has vertical turbine pumps; relift plant has horizontal centrifugal pumps. |
|