Wasco Dam

Picture of Wasco Dam, Oregon


Statistics

General

  • Region (Map): ................... Pacific Northwest
  • State (Map) ........................ Oregon
  • County ................................ Wasco
  • Project: ................................ Wapinitia
  • Dam type: ..........................  Earthfill
  • Location: ............................ 35 mi W of Maupin
  • Watercourse: ..................... Clear Creek
  • Reservoir: ........................... Clear Lake
  • Construction Date: ........... 1958-1959
  • National ID Number ......... OR00326
  • Hydrologic Unit Code .....

Dimensions


Hydraulics

  • Normal Water Surface Elev:       ......... 3514.4 ft
  • Hydraulic Height: ...................................  40.0 ft
  • Service Spillway Type:
  •    Uncontrolled  Crest    ..............................  Yes
  •    Crest Length    ..........................................  NA
  •    Gated      .....................................................   No
  •    Capacity at Elev: 3520.0 ft, ................. 170 cfs
  • Auxiliary Spillway ......................................   Yes
  •     Capacity at Elev. 3526.0 ft ................  450 cfs
  • Outlet Works Capacity at
  •     Elevation  3520.0 ft  ..........................   490 cfs 

Hydrology

  • Drainage Area: .................................    8.8 sq mi
  • Hydrometeorological Report               HMR 57
  • Flood Type: ........................... Nov-Feb General
  • Type Storm: ..................................Winter Event
  • Storm Duration: ........................................ 72 hrs
  • Probable Maximum Flood (PMF) Report:
  •   Peak Inflow: ...................................    13,000 cfs
  •   Inflow Volume: ........................... 14,200 acre-ft
  •   Flow Duration: .................................... 7.5 days
  •   PMF Routing MWS Elev.: .....................    NA
  •   Initial Routing Elev: .................................   NA
  •   Study Date: ................................ August 1994

    Dam modifications underway, revision likely to above data


Power Generation


Narration

 


Geology 

 Wasco Dam is in a narrow valley with steep slide slopes.  The left abutment juts out into the valley and at a height of 50 feet above the stream flattens off into a bench.  Ice or glacial deposits, causing ice or glacial melt water to discharge once blocked the stream channel over a bench a few hundred feet behind the left abutment.  A channel developed which extends from this rock bench to a point in the present channel a few hundred feet downstream from the dam site.  Bedrock at the lowest point of the old channel is about 15 feet above the reservoir flow line.  Overburden at the flow line on the right abutment consisted of 28 feet of gravel with excess sand and silt.  Boulders were hard, fresh andesite 2 to 3 feet in diameter.  Much of the over burden between flow line and the valley flow was undoubtedly quite permeable.


Links

 | Recreation  |

 | Dams Located by State | USBR Oregon Dams | Pacific Northwest Region Dams |

 | Owner: Lower Columbia Area Office, 1201 NE Lloyd Boulevard Suite 750,
Portland, OR 97232-1295, Phone: 503-872-2795, Fax: 503-872-2797

 | Operator:  Juniper Flat District Improvement Company,
 53333 Reservation Road, Maupin, OR  97037-9708, (541) 328-6380

 

 

Dams | Projects | Powerplants | Contact Us | Maps | Glossary | FAQ´s | Links